J102 Riverside school extension

Example Northgate Interiors Ltd, a fictional drylining subcontractor with three jobs over four month-ends. Look around; nothing here is saved. Sign up free to run yours

J102 Riverside school extension

for Calder Construction Ltd · order £260,000, tender margin 12.0%

Forecast final value £263,100 −£2,500 on last month
Forecast final cost £280,700 +£21,700 on last month
Forecast margin −£17,600 -6.7% · −9.17 pp
Cash outstanding £29,550 plus £4,950 retention

The CVR

This monthLast monthMovement
Forecast final measure £260,000 £260,000 £0
Recognised change £5,600 £5,600 £0
Less deductions / contras £2,500 £0 +£2,500
Forecast final value £263,100 £265,600 −£2,500
Forecast final cost £280,700 £259,000 +£21,700
Forecast margin −£17,600 £6,600 −£24,200
Forecast margin % -6.7% 2.5% −9.17 pp
Against tender−18.69 pp
Internal valuation (not cash) £168,100 £130,100 +£38,000
Margin to date (valuation less cost to date) −£6,000 £6,900 −£12,900
Over / (under) measure £5,600 £6,100 −£500
Accruals as a share of cost to date2.3%

Cost by head

Highlighted: a lazy or negative cost to complete
HeadBudgetLedgerAccrualsTo completeForecast finalMovedBasis
Own labour £90,000 £74,000 £1,800 £44,000 £119,800 +£15,800 Days x rate
Labour-only subs £50,000 £37,000 £0 £25,000 £62,000 +£5,000 Order +/- variations
Materials £60,000 £41,000 £2,200 £26,000 £69,200 +£1,000 Remeasure x current rates
Plant & access £12,800 £9,000 £0 £4,300 £13,300 £0 Budget less cost (avoid)
Sub-subcontract £8,000 £3,500 £0 £4,500 £8,000 £0 Order +/- variations lazy
Site overheads £8,000 £5,600 £0 £2,800 £8,400 −£100 Time-related

Why the margin moved

Forecast margin down 9.17 pp on last month, to -6.7% (−£24,200). Biggest movements: Own labour −£15,800; Labour-only subs −£5,000; Deductions / contras −£2,500.

Forecast final measure£0
Recognised change£0
Deductions / contras−£2,500
Own labour−£15,800
Labour-only subs−£5,000
Materials−£1,000
Plant & access£0
Sub-subcontract£0
Site overheads+£100
Total = margin movement−£24,200

Ties out to the margin movement.

Checks

3 to look at
  • 1. Value and cost entered for this monthOK
  • 2. Accruals carried from an earlier monthLook at this

    1 old accrual(s) carried 2+ months: chase or release.

    Why it matters: An accrual left in for another month may already be on the ledger (counted twice) or may never be invoiced. Old ones are the riskiest.

    What to do: Confirm each one is still owed, with a reason, or release it.

  • 3. Recognition overridden without a reasonOK
  • 4. Cost to complete is just budget less cost to dateLook at this

    Sub-subcontract.

    Why it matters: That isn't a forecast: it assumes the rest of the job goes exactly to budget, which hides overruns until the end.

    What to do: Rebuild cost to complete from the work left to do.

  • 5. Negative cost to completeOK
  • 6. Big margin move, or well above tenderLook at this

    Forecast margin moved -9.17 pp.

    Why it matters: Boards distrust a margin that jumps, or one far better than the tender, unless the reason is written down.

    What to do: Explain the move in the reasons box before the meeting.

  • 7. Main contractor valuing below our application, three months runningOK

Cash (not part of the margin)

Our application£171,000
Main contractor's gross valuation£165,000
Retention held£4,950
Deductions accepted£2,500
Net due£157,550
Paid to date (gross of CIS)£128,000
Outstanding£29,550
CIS deducted (memo)£12,800

Margin trend

Jun 202612.0%£31,200
Jul 20268.1%£21,000
Aug 20262.5%£6,600
Sep 2026-6.7%−£17,600