Northgate Interiors Ltd: cost value reconciliation

Month-end September 2026. Draft: not yet signed off. Worked example (fictional company).

Forecast loss on J102: provide for the full loss now (FRS 102 s21).
JobForecast valueForecast costMargin%MovedCash outstandingChecks to look at
J101 Station Road flats £488,750 £424,895 £63,855 13.1% −0.57 pp £50,480 2, 7
J102 Riverside school extension £263,100 £280,700 −£17,600 -6.7% −9.17 pp £29,550 2, 4, 6
J103 Mill Lane offices fit-out £152,000 £124,750 £27,250 17.9% +2.93 pp £34,700 3, 4, 6
Total£903,850£830,345£73,5058.1%£114,730

J101 Station Road flats, for Hallam Build Ltd

Forecast margin down 0.57 pp on last month, to 13.1% (−£2,795). Biggest movements: Materials +£8,000; Site overheads −£6,100; Deductions / contras −£4,200.

This monthLast monthMovement
Forecast final value£488,750£489,000−£250
Forecast final cost£424,895£422,350+£2,545
Forecast margin£63,855£66,650−£2,795
Margin %13.1%13.6%−0.57 pp
Internal valuation£273,750£224,000+£49,750
Cost to date (incl. accruals)£249,650
CashTo date
Applied£295,800
Valued by main contractor£270,400
Paid£205,200
Retention held£13,520
Outstanding£50,480
Why the margin moved£
Recognised change+£3,950
Deductions / contras−£4,200
Own labour−£595
Labour-only subs−£3,650
Materials+£8,000
Sub-subcontract−£200
Site overheads−£6,100
Margin movement−£2,795
Checks to look at
2. Accruals carried from an earlier month: Confirm 1 carried accrual(s).
7. Main contractor valuing below our application, three months running: 8.6% below our application this month.

J102 Riverside school extension, for Calder Construction Ltd

Forecast margin down 9.17 pp on last month, to -6.7% (−£24,200). Biggest movements: Own labour −£15,800; Labour-only subs −£5,000; Deductions / contras −£2,500.

Onerous contract: provide for the full loss now (FRS 102 s21).
This monthLast monthMovement
Forecast final value£263,100£265,600−£2,500
Forecast final cost£280,700£259,000+£21,700
Forecast margin−£17,600£6,600−£24,200
Margin %-6.7%2.5%−9.17 pp
Internal valuation£168,100£130,100+£38,000
Cost to date (incl. accruals)£174,100
CashTo date
Applied£171,000
Valued by main contractor£165,000
Paid£128,000
Retention held£4,950
Outstanding£29,550
Why the margin moved£
Deductions / contras−£2,500
Own labour−£15,800
Labour-only subs−£5,000
Materials−£1,000
Site overheads+£100
Margin movement−£24,200
Checks to look at
2. Accruals carried from an earlier month: 1 old accrual(s) carried 2+ months: chase or release.
4. Cost to complete is just budget less cost to date: Sub-subcontract.
6. Big margin move, or well above tender: Forecast margin moved -9.17 pp.

J103 Mill Lane offices fit-out, for Pennine Interiors Ltd

Forecast margin up 2.93 pp on last month, to 17.9% (+£5,500). Biggest movements: Forecast final measure +£5,000; Recognised change +£2,000; Materials −£1,500.

This monthLast monthMovement
Forecast final value£152,000£145,000+£7,000
Forecast final cost£124,750£123,250+£1,500
Forecast margin£27,250£21,750+£5,500
Margin %17.9%15.0%+2.93 pp
Internal valuation£69,000£30,500+£38,500
Cost to date (incl. accruals)£54,700
CashTo date
Applied£68,000
Valued by main contractor£66,000
Paid£28,000
Retention held£3,300
Outstanding£34,700
Why the margin moved£
Forecast final measure+£5,000
Recognised change+£2,000
Materials−£1,500
Margin movement+£5,500
Checks to look at
3. Recognition overridden without a reason: No reason given for VO-03.
4. Cost to complete is just budget less cost to date: Own labour, Labour-only subs, Plant & access, Sub-subcontract, Site overheads.
6. Big margin move, or well above tender: Forecast margin moved +2.93 pp.