Northgate Interiors Ltd: cost value reconciliation

Month-end August 2026. Draft: not yet signed off. Worked example (fictional company).

JobForecast valueForecast costMargin%MovedCash outstandingChecks to look at
J101 Station Road flats £489,000 £422,350 £66,650 13.6% −0.38 pp £25,200 4, 7
J102 Riverside school extension £265,600 £259,000 £6,600 2.5% −5.60 pp £20,280 2, 4, 6
J103 Mill Lane offices fit-out £145,000 £123,250 £21,750 15.0% 0.00 pp £28,025 4
Total£899,600£804,600£95,00010.6%£73,505

J101 Station Road flats, for Hallam Build Ltd

Forecast margin down 0.38 pp on last month, to 13.6% (−£950). Biggest movements: Recognised change +£6,600; Materials −£6,400; Site overheads +£5,350.

This monthLast monthMovement
Forecast final value£489,000£482,400+£6,600
Forecast final cost£422,350£414,800+£7,550
Forecast margin£66,650£67,600−£950
Margin %13.6%14.0%−0.38 pp
Internal valuation£224,000£159,400+£64,600
Cost to date (incl. accruals)£199,100
CashTo date
Applied£233,500
Valued by main contractor£216,000
Paid£180,000
Retention held£10,800
Outstanding£25,200
Why the margin moved£
Recognised change+£6,600
Own labour−£4,000
Labour-only subs−£500
Materials−£6,400
Plant & access−£2,000
Site overheads+£5,350
Margin movement−£950
Checks to look at
4. Cost to complete is just budget less cost to date: Sub-subcontract.
7. Main contractor valuing below our application, three months running: 7.5% below our application this month.

J102 Riverside school extension, for Calder Construction Ltd

Forecast margin down 5.60 pp on last month, to 2.5% (−£14,400). Biggest movements: Own labour −£10,000; Recognised change +£5,600; Labour-only subs −£5,000.

This monthLast monthMovement
Forecast final value£265,600£260,000+£5,600
Forecast final cost£259,000£239,000+£20,000
Forecast margin£6,600£21,000−£14,400
Margin %2.5%8.1%−5.60 pp
Internal valuation£130,100£82,000+£48,100
Cost to date (incl. accruals)£123,200
CashTo date
Applied£128,000
Valued by main contractor£124,000
Paid£100,000
Retention held£3,720
Outstanding£20,280
Why the margin moved£
Recognised change+£5,600
Own labour−£10,000
Labour-only subs−£5,000
Materials−£4,000
Plant & access−£500
Site overheads−£500
Margin movement−£14,400
Checks to look at
2. Accruals carried from an earlier month: Confirm 1 carried accrual(s).
4. Cost to complete is just budget less cost to date: Sub-subcontract.
6. Big margin move, or well above tender: Forecast margin moved -5.60 pp.

J103 Mill Lane offices fit-out, for Pennine Interiors Ltd

The forecast margin is unchanged from the tender at 15.0%.

This monthTenderMovement
Forecast final value£145,000£145,000£0
Forecast final cost£123,250£123,250£0
Forecast margin£21,750£21,750£0
Margin %15.0%15.0%0.00 pp
Internal valuation£30,500£0+£30,500
Cost to date (incl. accruals)£24,700
CashTo date
Applied£30,000
Valued by main contractor£29,500
Paid£0
Retention held£1,475
Outstanding£28,025
Why the margin moved£
Margin movement£0
Checks to look at
4. Cost to complete is just budget less cost to date: Own labour, Labour-only subs, Materials, Plant & access, Sub-subcontract, Site overheads.